儲能電站經(jīng)濟性及發(fā)展現(xiàn)狀分析
李廣洋,牛濤,閔玲
(中國能源建設(shè)集團江蘇省電力設(shè)計院有限公司,江蘇 南京 211102)
摘 要:列舉了儲能電站給電力系統(tǒng)中各方帶來的諸多效益,以某開展前期工作的江蘇地區(qū)鋰電池儲能電站為例,在給定的邊界條件下,按照《建設(shè)項目經(jīng)濟評價方法與參數(shù)》( 第三版) 評價其在削峰填谷的盈利模式情況下的經(jīng)濟可行性,選擇運行策略、初始投資成本、運營期限、度電補貼政策等因素進行敏感性分析,并探討影響儲能產(chǎn)業(yè)發(fā)展的關(guān)鍵性因素,給出相關(guān)應(yīng)對建議。
關(guān)鍵詞:儲能電站;收益分析;削峰填谷;經(jīng)濟分析;發(fā)展現(xiàn)狀
中圖分類號:TM715 文獻標(biāo)識碼:A 文章編號:1007-3175(2019)01-0001-04
Analysis of Economics and Development Status of Energy Storage Power Station
LI Guang-yang, NIU Tao, MIN Ling
(China Energy Engineering Group Jiangsu Power Design Institute Co., Ltd, Nanjing 2111 02, China)
Abstract: This paper enumerated the benefits brought by the various parties of the energy storage power station in the power system. Taking a lithium battery energy storage power station in Jiangsu as an example, under the given boundary conditions, this paper evaluated its economic feasibility in the case of peak-cutting and valley-filling profit model according to "economic evaluation method and parameters of construction projects" (3rd Edition). Sensitivity analysis was carried out by selecting factors such as operation strategy, initial investment cost, operation period and power subsidy policy etc, the key factors affecting the development of energy storage industry were discussed and the relevant suggestions were given.
Key words: energy storage power station; income analysis; peak-cutting and valley-filling; economic analysis; development status
參考文獻
[1] 劉英軍,劉暢,王偉,等. 儲能發(fā)展現(xiàn)狀與趨勢分析[J]. 中外能源,2017,22(4):80-88.
[2] 陳建斌,胡玉峰,吳小辰. 儲能技術(shù)在南方電網(wǎng)的應(yīng)用前景分析[J]. 南方電網(wǎng)技術(shù),2010,4(6):32-36.
[3] 王建軍,黃阮明,楊增輝. 華東地區(qū)抽水蓄能電站的節(jié)能效益分析[J]. 華東電力,2012,40(4):613-616.
[4] 孫振新,劉漢強,趙喆,等. 儲能經(jīng)濟性研究[J].中國電機工程學(xué)報,2013,33(S1):54-58.
[5] 許弈飛,曹新雅. 動力電池梯級利用回收模式與應(yīng)用研究[J]. 科技與創(chuàng)新,2018(9):111-112.
[6] 許守平,李相俊,惠東. 大規(guī)模電化學(xué)儲能系統(tǒng)發(fā)展現(xiàn)狀及示范應(yīng)用綜述[J]. 電力建設(shè),2013,34(7):73-80.