超特高壓變電站便攜式氣動短路接地裝置研制及應(yīng)用

來源:電工電氣發(fā)布時間:2017-09-21 13:21 瀏覽次數(shù):16
超特高壓變電站便攜式氣動短路接地裝置研制及應(yīng)用
 
吳勝,廖軍,黃偉民
(國網(wǎng)安徽省電力公司檢 修公司, 安徽 合肥 230601)
 
    摘 要:超高壓及特高壓變電站因其電壓等級高,安全距離大,使得設(shè)備垂直高度大,給接地線的裝拆帶來巨大挑戰(zhàn)。針對超高壓及特高壓變電站裝拆接地線的需求,研制了一種便攜式氣動短路接地裝置,介紹了短路接地裝置的結(jié)構(gòu)設(shè)計、部件設(shè)計,并計算短路接地裝置的相關(guān)參數(shù)。該裝置成功應(yīng)用于超高壓及特高壓變電站設(shè)備裝拆接地線,具有體積小、重量輕、操作簡單、安全可靠等特點(diǎn),為設(shè)備檢修工作帶來巨大便利。
    關(guān)鍵詞:超高壓;特高壓;變電站;便攜式;氣動;短路接地
    中圖分類號:TM645     文獻(xiàn)標(biāo)識碼:B      文章編號:1007-3175(2017)09-0056-04
 
Development and Application of Portable Pneumatic Grounding Device in Ultra-High Voltage Substation
 
WU Sheng, LIAO Jun, HUANG Wei-min
(State Grid Anhui Maintenance Company, Hefei 230601, China)
 
    Abstract: The ultra-high and extra-high voltage transformer substations have the high voltage level and the long safe distance with the high vertical height of the equipment, which brings great challenges for the installation and disassembly of the grounding wire. According to the requirement of the installation and disassembly of the grounding wire of ultra-high and extra-high voltage transformer substation, this paper developed a kind of portable pneumatic grounding device, introduced the structure and component design of short-circuit grounding device and calculated its related parameters. This device is successfully applied in the ultra-high and extra-high voltage transformer substations for the equipment to install and remove the grounding wire, with the features such as small volume, light weight, simple operation, safety and reliability and so on, which brings great convenience for the equipment overhaul work.
    Key words: ultra-high voltage; extra-high voltage; transformer substation; portable; pneumatic; short-circuit grounding
 
參考文獻(xiàn)
[1] 張本賢.電力安全生產(chǎn)及防護(hù)[M ].北京:中國電力出版社,2014.
[2] 國家電網(wǎng)公司.國家電網(wǎng)公司電力安全工作規(guī)程(變電部分)[M].北京:中國電力出版社,2009.
[3] 王曉斌.變電站防止接地線事故的措施[J].中小企業(yè)管理與科技,2011(36):292.
[4] 盛連軍,張滕飛,韓忠華,等.一種新型長柄多角度短路接地線的研究[J].華東電力,2011,39(10):1751-1753.
[5] 周軍,郭凱翔,李雪松,等.500 kV輸電線路停電檢修裝設(shè)接地線的措施分析[J].內(nèi)蒙古電力技術(shù),2002,20(6):42-43.
[6] 虞澤.攜帶型短路接地線的改進(jìn)[J].云南電力技術(shù),2008,36(1):40-41.
[7] 巫水萍,張瑜,臧和平.新型變電站接地線管理系統(tǒng)設(shè)計和實現(xiàn)[J].電氣技術(shù),2012(8):77-80.
[8] 王東海,吳健.高壓電纜接地線安裝質(zhì)量引起的故障分析[J].電線電纜,2005(1):34-35.
[9] 戴克銘.正確使用攜帶型短路接地線[J].電力安全技術(shù),2011,13(11):20-24.
[10] 戴克銘.攜帶型短路接地線截面積的驗算[J].電力安全技術(shù),2004,6(5):37.